Nant Pa Nga Hydropower Project which can distribute power to MSMEs in Homalin finished 41 percent
Hsu / Yoon (NSS) – July 11
The State Administration Council (SAC) released the news that 41% construction of Nant Pa Nga Hydropower Project which can give electricity coverage to the MSMEs in Homalin Township, in Sagaing Region has been completed.
Sagaing Regional Chief Minister Myat Kyaw inspected the hydropower project on 9th July.
After the construction of the small hydropower project, the local areas including Homalin Township and the MSMEs nearby will be able to enjoy electric power upon completion of the project.
“The generating power will be about 6 megawatts and 34.68 million kilowatt hours are expected to generate and it is important to produce within the targeted time.” the Regional Chief said.
The project is being implemented on Nant Pa Nga creek near Naar Tha Kyeik village, Homalin Township and it is a Gravity Dam type.
It is reported that the hydropower project construction will be finalized in the 2024-25 fiscal year and up to now 41.71% of construction work has been accomplished.
Comments :
0 comments
မကွေးတိုင်းဒေသကြီး၊ စလင်းမြို့နယ်၊ အုတ်ဖိုကန်ကျေးရွာ၊ မင်းဘူး- စလင်းကားလမ်းပေါ်တွင် သစ်ပင်လဲကျမှုဖြစ်ပွား
ASEAN high-level meeting (SOM)အစည်းအဝေးအတွင်း မြန်မာ့နိုင်ငံရေးကိုထည့်သွင်း ဆွေးနွေးဖွယ်မရှိသေးကြောင်း အင်ဒိုနီးရှားအစိုးရပြော
RELATED POSTS
20 Sep 2024 | လူမှုရေး,ပြည်တွင်း
20 Sep 2024 | လူမှုရေး,ပြည်တွင်း
19 Sep 2024 | လူမှုရေး,ပြည်တွင်း
19 Sep 2024 | လူမှုရေး,ပြည်တွင်း